Road excavation work to extend an intermediate gas main down A Street is expected to start Friday, February 15, 2019. This work is a resumption of what had began last summer and was halted by the National Grid strike.
A parking ban will in effect weekdays during the hours of 9:30 am to 3:30 pm. Today no parking signs were posted at the corner of Binford Street & A Street to Wormwood Street.
The work route will continue down A Street to Melcher St and then turn on to Necco Street. The no parking permit is effective through March 8, 2019.
If you park on A Street or Melcher Street, keep an eye out for parking restrictions by block as the work progresses.