- Paving around Sleeper Street beside and in front of the garage?
- New Bridges: one bridge abutment poured in concrete, the other being formed now?
- Pile work started along the Harborwalk?
- The majority of the playground equipment delivered to the lay down yard?
- Concrete sidewalk sample panels poured?
- Locust posts delivered?
If you saw all of the items above, you have a keen sense of observation and a good memory.
Mini Pile Installation |
Locust Posts |
Here is what to keep an eye out for in the next 2-3 weeks:
Granite Quarry Stones |
- Continued work along Sleeper Street and on the garage, including curbing, paving, etc.
- The majority of the work over the next few weeks will be installing the piles along the Harborwalk
- The second bridge abutment will be poured with concrete
- Electrical work
- Prepping the play ship for installation
- Form work for the amphitheater
- Granite stones (from the quarry) will begin to be delivered
If you have any questions or concerns, please contact Lauren Bryant with Boston Parks & Recreation Department.